0
We will call you back in 25 seconds
Order a call

Status of construction of the residential complex “IQ House” as of 26.09.2023

Status of construction of the residential complex “IQ House” as of 26.09.2023
Status of construction of the residential complex “IQ House” as of 26.09.2023
Status of construction of the residential complex “IQ House” as of 26.09.2023
Status of construction of the residential complex “IQ House” as of 26.09.2023
Status of construction of the residential complex “IQ House” as of 26.09.2023
Status of construction of the residential complex “IQ House” as of 26.09.2023
Status of construction of the residential complex “IQ House” as of 26.09.2023
Status of construction of the residential complex “IQ House” as of 26.09.2023
Status of construction of the residential complex “IQ House” as of 26.09.2023
Status of construction of the residential complex “IQ House” as of 26.09.2023
Status of construction of the residential complex “IQ House” as of 26.09.2023

01 /01

Section 1 The masonry of the basement walls is 95% complete. Reinforcement of the walls and columns of the 8th floor is completed. Concreting of the walls and columns of the 8th floor is 33% complete. Waterproofing of the foundation has been completed by 25%. Section 2 The masonry of the walls of the basement is 95% complete. Reinforcement of the staircases and landings on the 4th floor has been completed. Concreting of stairwells and landings on the 4th floor is completed. Completion of the exterior walls of the 9th floor. Installation of windows on the 8th and 10th floors is 50% complete. The screed on the technical floor has been completed. The waterproofing of the foundation has been completed by 50%. Plastering of apartments from the 3rd to the 5th floors is completed. Plastering of the 6th floor apartments is 50% complete. Section 3 Installation of vertical elements of the 9th floor is completed. Reinforcement of the floor slab of the 10th floor has begun. Completion of the exterior walls of the 7th floor. The masonry of the basement walls has been completed. Works on waterproofing the foundation by 70% are in progress.
envelope

Find out first about the company's news

close form

Даруємо квартиру за донат!

Даруємо квартиру за донат!