Section 1
Casting of the floor slab of the ground floor is completed.
Reinforcement and casting of columns of the 1st floor has begun.
Section 2
Pile driving is in progress.
This site uses cookies to store data. If you remain on the site, you agree to work with these files.
Ваше ім'я*
Ваш номер телефону*
Які житлові комплекси Вас цікавлять?
Оберіть зручний час для розмови*