Construction state of the Family Plaza residential complex 6.07.2022

Construction state of the Family Plaza residential complex 6.07.2022

Construction status of the Family Plaza residential complex as of 6.07.2022

Section 1
– Work on external sewerage networks has been completed.
– Works on internal house networks (water supply and sewerage) have been completed.
– The masonry of the external and internal walls of the commercial premises is completed.
– The entrance is being finished.

Section 2
– Facade finishing works have been completed.
– Plastering of the staircase has been completed.
– Work is underway on internal power supply networks.
– The external and internal walls of the commercial building are 90% complete.

Section 3
– Completed masonry of the internal and external walls of the basement
– Facade decoration is 70% complete.

Section 4
– Completed laying of internal and external walls of the basement
– Facade decoration is 50% complete.

Section 5
– Laying of external and internal walls of the 10th floor is in progress.

Section 6
– Concreting of vertical elements of the 6th floor is in progress.

Section 7
– Concreting of the vertical elements of the basement is underway.

Section 12
– Concreting of vertical elements of the 9th floor is underway.
– Laying of external and internal walls of the 4th floor is in progress.