Construction state of the Union residential complex as of February 3, 2023

Construction state of the Union residential complex as of February 3, 2023

Section A
Finishing of the entrance is completed.
The lobby is 50% finished.
The paving stones for the entrance to the section have been laid.

Section B
Finishing of the entrance is 90% complete.
The facade is 90% finished.

Section B
Installation of water supply and sewerage networks has begun.
Laying of inter-apartment and interior walls has been completed.
Glazing of the 7th floor has been completed.

Section D
Grillage has been completed.
Concreting of the vertical elements of the basement is completed.

Section D
Work on pile driving is nearing completion.
The installation of grillage has begun.

Commercial section
Concreting of vertical elements has been completed.
Slab formwork has been completed.