Construction status of the U ONE residential complex as of 02.02.2023

Construction status of the U ONE residential complex as of 02.02.2023

Section 3
Installation of vertical elements of the 2nd and 3rd floors is completed.
The formwork of the floor slabs of the 2nd and 3rd floors has been completed.

Section 4
Reinforced concrete piles have been pressed by 90%.
The installation of monolithic grillage is 50% complete.

Section 2
Reinforced concrete piles have been pressed by 70%.