Сonstruction state of the residential complex “U ONE” as of 01.09.2023

Сonstruction state of the residential complex “U ONE” as of 01.09.2023

Section 3
The masonry of the outer walls of the 13th floor has been completed.
Glazing of the 10th floor is completed.
Laying of the internal walls of the 8th floor is in progress.
Plastering of staircases is 80% complete.
Roofing is in progress.

Section 4
Installation of the floor slab of the 13th floor is completed.
Laying of the external walls of the 9th floor is in progress.

Section 2
Installation of the floor slab of the 9th floor is in progress.

Section 1
Installation of monolithic grillage is 95% complete.
Installation of vertical elements of the 1st floor is 90% complete.
Work is underway on the installation of external water supply and sewage networks.