Section 1-2
The installation of monolithic retaining walls in the open courtyards of the 1st floor has been completed.
Facade works on the 1st floor are 50% complete.
Paving works are 40% complete.
Works on finishing the lobby are in progress.
Section 3-4
The installation of monolithic retaining walls in the open courtyards of the 1st floor has been completed.
The paving works are 40% complete.
Facade works on the 1st floor are 50% complete.
Works on finishing the lobby are in progress.
Section 5
The interior decoration of the entrances is 40% complete.
Facade works on the 1st floor are in progress.