Section 1
– Excavation of the pit has begun.
Section 2
– Installation of the floor slab of the 2nd floor has begun.
– Concreting of wall columns is completed.
– Installation of the floor slab of the 1st floor is completed.
Section 3
– Installation of the floor slab of the 1st floor has begun.
– The construction of vertical elements of the 1st floor is 80% complete.