Section 1
The excavation of the pit is completed.
Concreting of the foundation slab has been completed.
Section 2
Installation of the floor slab of the 3rd floor is completed.
Installation of the floor slab of the 4th floor has begun.
The construction of vertical elements of the 4th floor is completed.
Section 3
Completion of vertical elements of the 2nd floor.
Installation of the floor slab of the 2nd floor is completed.