0
We will call you back in 25 seconds
Order a call

Construction state of the Family Plaza residential complex as of 11.1.2022

Construction state of the Family Plaza residential complex as of 11.1.2022
Construction state of the Family Plaza residential complex as of 11.1.2022
Construction state of the Family Plaza residential complex as of 11.1.2022
Construction state of the Family Plaza residential complex as of 11.1.2022
Construction state of the Family Plaza residential complex as of 11.1.2022
Construction state of the Family Plaza residential complex as of 11.1.2022
Construction state of the Family Plaza residential complex as of 11.1.2022
Construction state of the Family Plaza residential complex as of 11.1.2022
Construction state of the Family Plaza residential complex as of 11.1.2022
Construction state of the Family Plaza residential complex as of 11.1.2022

01 /01

Section 1 The hall is 60% finished. Section 2 The entrance is 60% finished. Finishing of the hall is in progress. Section 3 Works on in-house networks (electricity supply) are completed. Plastering of apartments is completed. The entrance is 30% finished. Section 4 Completed work on internal house networks (water supply and sewerage). Completed work on internal house networks (electricity). Plastering of apartments is in progress. Finishing of the entrance has begun. Section 5 Glazing of the section has begun. Finishing of the facade has begun. Work has begun on the in-house networks (water supply and sewerage). Section 6 Laying of the external walls of the 10th floor is completed. Laying of the internal walls of the 8th floor is in progress. Section 7 Concreting of vertical elements of the 6th floor is in progress. Formwork of the floor slab of the 6th floor is in progress. Work is underway on the laying of the outer walls of the 3rd floor. Section 8 Concreting of the vertical elements of the first floor has been completed. Formwork for the floor slab of the first floor is in progress. Section 12 Glazing works have been completed. Works on internal house networks (water supply and sewerage) are in progress. Facade finishing is in progress. Plastering of apartments is in progress.
envelope

Find out first about the company's news

close form

Даруємо квартиру за донат!

Даруємо квартиру за донат!