Construction state of the Family Plaza residential complex as of 12.10.2022

Construction state of the Family Plaza residential complex as of 12.10.2022

Section 1
– Finishing of the entrance is completed.
– The lobby is being finished.

Section 2
– Installation of the elevator is completed.
– Finishing of the entrance is in progress.
– Finishing of the hall has begun.

Section 3
– Installation of the elevator is completed.
– Completed work on internal house networks (water supply and sewerage).
– Works on internal house networks (electricity supply) are in progress.
– Plastering of apartments has begun.

Section 4
– Finishing of the facade is completed.
– Installation of the elevator is completed.
– Works on internal house networks (water supply and sewerage) are in progress.
– Work is underway on the internal house networks (electricity).
– Plastering of apartments has begun.

Section 5
– Completed laying of external and internal walls of the basement.

Section 6
– Monolithic works are completed.
– Laying of the outer walls of the 8th floor is completed.
– Laying of the internal walls of the 4th and 5th floors is in progress.

Section 7
– Concreting of vertical elements of the 4th floor is completed.
– Formwork for the floor slab of the 4th floor is in progress.
– Work has begun on the laying of the outer walls of the 1st floor.

Section 8
– Concreting of the vertical elements of the basement has been completed.
– The formwork of the basement floor slab is in progress.

Section 12
– Completed laying of the outer walls of the 10th floor.
– Work is underway on the internal house networks (water supply and sewerage).
– Glazing works are in progress.
– Facade finishing has begun.
– Plastering of apartments has begun.