0
Order a call

News

Construction state of the residential complex A5 as of 10.28.2022

28.10.2022

Construction state of the residential complex A5 as of 10.28.2022

Concreting of the vertical elements of the 3rd floor has been completed. Reinforcement of the floor slab on the 3rd...

blago developer received a certificate of appreciation from the Association of Interventional Oncologists of Ukraine

27.10.2022

blago developer received a certificate of appreciation from the Association of Interventional Oncologists of Ukraine

Our company, represented by CEO Roman Korzhak, received an award from the Association of Interventional Oncologists of Ukraine for supporting...

Updated photos of Franko River Club as of 26.10.2022

26.10.2022

Updated photos of Franko River Club as of 26.10.2022

Franko River Club is a cottage community where each house has its own personal style, without disturbing the holistic perception...

Construction state of the residential complex “Avtorskyi” as of 25.10.2022

25.10.2022

Construction state of the residential complex “Avtorskyi” as of 25.10.2022

Section 1-2 Reinforcement and concreting of the vertical elements of the parking lot has been completed. Tile installation on the...

Construction state of Comfort Park as of 10.25.2022

25.10.2022

Construction state of Comfort Park as of 10.25.2022

Section 13 The entrances are 95% complete. Installation of tiles in the entrances has been completed. Section 14 Facade finishing...

Construction state of the residential complex Shokolad as of 10.24.2022

24.10.2022

Construction state of the residential complex Shokolad as of 10.24.2022

Section 1-2 The installation of monolithic retaining walls in the open courtyards of the 1st floor has been completed. Facade...

Construction state of the residential complex Shokolad as of 10.24.2022

24.10.2022

Construction state of the residential complex Shokolad as of 10.24.2022

Section 1-2 The installation of monolithic retaining walls in the open courtyards of the 1st floor has been completed. Facade...

Construction state of Main House as of 10.21.2022

21.10.2022

Construction state of Main House as of 10.21.2022

Section 1 Facade works are 50% complete. The plastering of the apartments on the 13th floor has been completed. Installation...