Construction status of the residential complex “SKYGARDEN” as of 22.08.2013

Construction status of the residential complex “SKYGARDEN” as of 22.08.2013

Sections 1-2
The works on crushed stone preparation for the foundation grillage have been completed.
Work has begun on the installation of monolithic grillage.
The pile field for 2 sections has been completed.
Installation of an auxiliary tower crane is in progress.

Section 3
The pile field has been completed.

Sections 4-5
The pit has been completed.
The pile field is 45% complete.
The pit is 50% complete (section 5).

Work has begun on the construction of a transformer substation.