Construction status of the residential complex “Main House” as of 04.09.2023

Construction status of the residential complex “Main House” as of 04.09.2023

Section 1
Finishing of entrances is completed.
Glazing of the commercial floor is completed.
Installation of elevators has been completed.
Facade works on the commercial floor have begun.

Section 2
Installation of a hinged ventilated facade has begun.

Parking lot
The installation of the concrete floor of the parking lot has begun.

Landscaping
Landscaping is in progress.
Paving is 80% complete.