Section B
The hall is 90% finished.
Section C
The hall is 90% finished.
Section D
Monolithic works on the section are completed.
Laying of the outer walls of the 8th floor is in progress.
Laying of the internal walls of the 4th floor has begun.
The parapet is being laid.
Section D
Concreting of vertical elements of the 10th floor is in progress.
Laying of the external walls of the 8th floor is in progress.
Laying of the internal walls of the 2nd floor is in progress.
Laying of the parapet is in progress.
Commerce
Commercial glazing is completed.