Section 1-2
Testing of piles has been completed.
Works on construction site arrangement for construction works are in progress.
The drainage of the first stage pits is 28% complete.
Works are underway to construct the fuel field by 30% in section 1.
Works are underway to construct the fuel field by 10% in section 2.