0
We will call you back in 25 seconds
Order a call

Construction dynamics of Family Plaza RC: March – May 2023

Construction dynamics of Family Plaza RC: March – May 2023
Construction dynamics of Family Plaza RC: March – May 2023
Construction dynamics of Family Plaza RC: March – May 2023
Construction dynamics of Family Plaza RC: March – May 2023
Construction dynamics of Family Plaza RC: March – May 2023
Construction dynamics of Family Plaza RC: March – May 2023

01 /01

We keep moving forward and implementing comfortable housing projects for the whole family. The results of the construction of Family Plaza make our team proud and the apartment owners delighted. And it's not just about aesthetics, but also about the amount of work done. For example, as of March 2023, it has been completed:   Section 1 Transferred to the management company.   Section 2 Finishing of the hall is completed.   Section 3 Finishing of the entrance is completed. Finishing of the hall has begun.   Section 4 Finishing of the entrance is 95% complete. Finishing of the hall has begun.   Section 5 Plastering of apartments is completed. Facade finishing is 95% complete. Works on in-house networks (electricity supply) have been completed by 80%. The staircase and garages have been plastered. The entrance has been finished by 30%.   Section 6 Glazing has been completed. Plastering of apartments has been completed. Plastering of the staircase and garages is completed. Work on the in-house water and sewerage networks has been completed. The facade is 90% finished. Work has begun on the in-building networks (electricity supply).   Section 7 The construction of floors has been completed. The external walls of the 6th-10th floors have been constructed. The internal walls of the 6th and 7th floors have been constructed, and the construction of the 8th and 10th floors is in progress. Glazing of the floors has begun and is in progress.   Section 8 Floors 3-5 have been erected. The construction of the 6th floor is in progress. The external and internal walls of the 1st and 2nd floors have been constructed.   Sections 9-10 The development of the pit is completed. Reinforcement of the foundation slab has been completed. Work on the construction of the basement has been completed. Concreting of vertical elements of the 1st residential floor is 90% complete. Installation of formwork for the floor slab of the 1st residential floor is underway.   Section 12 Commercial glazing is completed. Work is underway on the in-building networks (electricity supply). Finishing of the entrance is in progress.
envelope

Find out first about the company's news

close form

Даруємо квартиру за донат!

Даруємо квартиру за донат!