Section 1
Installation of reinforced plastic windows is in progress.
Finishing of façade has begun.
Installation of a PVC-membrane on the roof is almost completed.
Works on the installation of storm water drains and domestic sewerage system are in progress.
Sections 2-2a
Installation of the 8th floor intermediate slab is complete.
Preparatory work for the installation of walls and columns on the 9th floor has begun.
Bricklaying of the external walls of the 3rd floor has begun.
Section 10
The construction of the floor parapet is complete.
Plastering of apartments on the 8th floor is complete.
Section 9
The bricklaying of the external walls of the 11th floor is in progress.
Plastering of apartments on the 5th floor is in progress.
Section 8
The bricklaying of the external walls of the 10th floor is complete.
Plastering of apartments on the 6th floor is in progress.
Sections 6-7
Installation of monolithic grid foundation is complete.
The bricklaying of the walls and columns of the ground floor has begun.