Construction state of the Chocolate residential complex as of 18.08.2021

Construction state of the Chocolate residential complex as of 18.08.2021

Section 1,2
Installation of windows is complete.
Façade work is in progress.
Apartment plastering has begun.

Section 3,4
Roofing is in progress.
Bricklaying of the exterior walls of the 6th and 7th floors is complete.
Bricklaying of the interior walls of the 6th and 7th floors is in progress.

Section 5
Concrete casting of the vertical members of the 3rd floor is complete.
Concrete casting of the 4th floor slab panel has begun.
Internal bricklaying of the 1st floor has begun.