Construction state of the Family Plaza residential complex as of 17.11.2020
Construction state of the Family Plaza residential complex as of 17.11.2020
Section 1
Casting of the floor slab of the ground floor is completed.
Reinforcement and casting of columns of the 1st floor has begun.
Section 2
Pile driving is in progress.