Section 1
Elevator is installed.
Interior work on the entrance lobby is in progress.
Section 2
Interior work on the entrance lobby is in progress.
Installation of an elevator is almost complete.
Section 3
Installation of an elevator is almost complete.
Interior work on the entrance lobby is in progress.
Sections 4-6
Bricklaying of interior walls on the 9th floor has begun.
Roof screeding is laid.
Installation of windows is in progress.
Sections 7-9
Facade works are in progress.
Sanitary engineering work is in progress.
Plastering is in progress.
Sections 10-12
Works on floor slab panel on the 5th and 6th floors are in progress.