Pre-construction activities for the installation of a basketball court are underway.
Buildings №1-10
Taken into use.
Buildings №9,10
Interior work on the entrance lobby is almost complete.
Beautification of the adjacent territory is in progress.
The arrangement of commercial premises is in progress.
Finishing of the stairs to the entrance is complete.
Plastering of commercial premises is complete.
Commercial premises are being built using gas concrete blocks.
Building №11
Elevator is installed.
Interior work on the entrance lobby is in progress.
Plastering of commercial premises is complete.
Commercial premises are being built using gas concrete blocks.
Buildings №12 та 13.
Interior work on the entrance lobby is in progress.
Plastering of commercial premises is complete.
Commercial premises are being built using gas concrete blocks.