✅Cottages №14,20,30 and 33 are on the stage of working on facade finish.
✅Pavement works are being carried out on the streets between cottages 30-33 and 24-27. Electric cables, networks for outdoor street lighting, video surveillance and internet cable are set up in this area as well.
✅Gas supply is already available in all cottages of the town.
✅Chimney caps are installed in cottages №20-30.