Construction dynamics of IQ House: April-October 2023

11.10.2023

Construction dynamics of IQ House: April-October 2023

We love watching the pace of construction of our projects. Every month they become bigger and more beautiful. This is...

Construction state of the U ONE residential complex as of 11.10.2023

11.10.2023

Construction state of the U ONE residential complex as of 11.10.2023

Section 3 Glazing of the 11th floor is completed. Glazing of the 12th floor is 80% complete. Completed laying of...

Updated photos of the Parus residential complex as of 10.10.2023

10.10.2023

Updated photos of the Parus residential complex as of 10.10.2023

PARUS is the perfect place to live! This is an exquisite elite class property in the centre of Ivano-Frankivsk. The...

Construction state of the residential complex “Avtorskyi” as of 09.10.2023

09.10.2023

Construction state of the residential complex “Avtorskyi” as of 09.10.2023

Sections 1-2 Works on the improvement of the adjacent territory have been completed by 80%. The car park lighting has...

Construction state of the residential complex “A5” as of 05.10.2023

05.10.2023

Construction state of the residential complex “A5” as of 05.10.2023

✅Sections 1-2 Laying of the internal walls of the 8th and 11th floors is completed. The masonry of the internal...

Construction state of the IQ House residential complex as of 04.10.2023

04.10.2023

Construction state of the IQ House residential complex as of 04.10.2023

Section 1 The masonry of the basement walls is completed. Concreting of the walls and columns of the 8th floor...

Dynamics of construction of the Parkova Alley residential area: February – September 2023 💚

03.10.2023

Dynamics of construction of the Parkova Alley residential area: February – September 2023 💚

We continue to build our projects without resting on our laurels. Every month we are getting closer to the completion...

Construction state of the residential complex “MAIN HOUSE” as of 03.10.2023

03.10.2023

Construction state of the residential complex “MAIN HOUSE” as of 03.10.2023

Section 1 Facade works on the commercial floor are 50% complete. Section 2 Installation of the hinged-ventilated facade is 25%...