News
08.12.2022
Construction state of the Family Plaza residential complex as of 08.12.2022
Section 1 The hall is being finished. Section 2 Finishing of the entrance is nearing completion. The hall is being...
01.12.2022
Construction state of the residential complex “U ONE” as of 01.12.2022
Section 3 Work is nearing completion on pressing reinforced concrete piles. The installation of monolithic grillage is 60% complete. Installation...
30.11.2022
Construction state of the Union residential complex as of 11.30.2022
Section 1 The entrance is 80% finished. Finishing works on the commercial floor facade have been completed. Section 2 The...
30.11.2022
Construction state of the residential complex “Parkova Alley” as of 11.30.2022
Section 3 Installation of the floor slab on the 11th floor is in progress. Laying of external walls of the...
22.11.2022
Construction state of the residential complex Shokolad as of 11.22.2022
🏗Section 1-4 We are completing the facade works on the 1st floor. Finishing works on the hall are completed. Work...
22.11.2022
Construction state of the residential complex A5 as of 11.22.2022
Concreting of the floor slab of the 5th floor is completed. Concreting of the vertical elements of the 6th residential...
18.11.2022
Construction state of the IQ House residential complex as of 11.18.2022
Section 1 Completing the excavation of the pit. Section 2 Installation of the floor slab of the 2nd floor is...
18.11.2022
Updated photos of the Royal Hall residential complex as of 11.18.2022
Royal Hall is a residential complex that emphasizes your status! 💎 Walking access to all the most important locations of...