0
Order a call

News

Construction state of the Family Plaza residential complex as of February 20, 2023

20.02.2023

Construction state of the Family Plaza residential complex as of February 20, 2023

Section 1 Transferred to the management company. Section 2 Finishing of the entrance is completed. Finishing of the hall is...

Construction state of the residential complex Chocolate as of 17.02.2023

17.02.2023

Construction state of the residential complex Chocolate as of 17.02.2023

Section 1-4 Transferred to the management company. Section 5 Transferred to the management company.

Updated photos of the Parus complex as of 02.17.2023

17.02.2023

Updated photos of the Parus complex as of 02.17.2023

PARUS is the perfect place to live! This is an exquisite elite class real estate in the center of Ivano-Frankivsk....

Construction state of the residential complex “Avtorskyi” as of 17.02.2023

17.02.2023

Construction state of the residential complex “Avtorskyi” as of 17.02.2023

Section 1-2 Clinker tiling of the walls of penthouses in 2 sections has been completed. Finishing of stairwells and corridors...

Construction state of the U ONE residential complex as of 02.16.2023

16.02.2023

Construction state of the U ONE residential complex as of 02.16.2023

Section 3 Installation of vertical elements of the 4th floor is completed. Section 4 Completed work on the pressing of...

Construction state of the residential complex “A5” as of 02.16.2023

16.02.2023

Construction state of the residential complex “A5” as of 02.16.2023

The exterior walls of the 5th floor are 60% complete. Laying of the internal walls of the 4th floor is...

Construction state of the residential complex “IQ House” as of February 15, 2023

15.02.2023

Construction state of the residential complex “IQ House” as of February 15, 2023

Section 1 Installation and concreting of the 1st floor has been completed. The construction of vertical elements of the 2nd...

Construction state of the residential complex “MAIN HOUSE” as of 10.02.2023

10.02.2023

Construction state of the residential complex “MAIN HOUSE” as of 10.02.2023

Section No. 1 Facade works are 80% complete. Entrances are 30% finished. Installation of entrance doors to apartments has begun....