28.11.2023
Construction state of the Union residential complex as of 28.11.2023
Section B The hall is 90% finished. Section C The hall is 90% finished. Section D Laying of the internal...
27.11.2023
Construction state of the Parkova Alley residential complex as of 27.11.2023
Section 3 Installation of doors has been completed. Gas supply to the apartments is in progress. Concreting of the concrete...
24.11.2023
Bandera Street infrastructure fills life with a new quality
What are the criteria for choosing a new home before buying? The first and often decisive factor is the location...
24.11.2023
Construction state of the IQ House residential complex as of 24.11.2023
Section 1 Waterproofing of the foundation is 70% complete. The installation of vertical elements of the technical floor has been...
21.11.2023
Franko River Club cottage community | 21.11.2023
Franko River Club is a cottage community where each house has its own personal style, without disturbing the holistic perception...
21.11.2023
blago received the “Company of the Year 2022” award
We have added another distinction to our list of achievements. Thanks to our super-motivated team and desire to change the...
21.11.2023
Family Plaza RC construction dynamics: June – November 2023
We compare changes at the construction site from month to month and record the growth of each section. Here is...
17.11.2023
Construction state of the residential complex “SKYGARDEN” as of 17.11.2023
Section 1 Concreting of vertical elements of the 2nd residential floor is completed. Reinforcement of the floor slab of the...