Section 1
The entrances are 90% finished.
Installation of heating networks is 80% complete.
Section 2
Installation of aluminum facade glazing is 40% complete.
Parking lot
The foundation slab of the 4th bay of the parking lot has been completed.
Installation of vertical elements of the 4th parking bay is completed.