Section A
Finishing of the entrance is completed.
The lobby is 90% finished.
Section B
Finishing of the entrance is 90% complete.
Section C
Installation of water supply and sewerage networks is in progress.
The installation of in-building power supply networks is in progress.
Facade finishing works are 50% complete.
Plastering of apartments and staircases is in progress.
Section D
Concreting of vertical elements of the 2nd floor has been completed.
Laying of the floor slab of the 2nd floor is in progress.
Section E
Concreting of vertical elements of the basement is completed.
Concreting of the basement floor slab is completed.
Concreting of vertical elements of the 1st floor has begun.
Commerce
Laying of the outer walls of the commercial building is in progress.