Construction state of the U ONE residential complex as of 02.16.2023
Section 3
Installation of vertical elements of the 4th floor is completed.
Section 4
Completed work on the pressing of reinforced concrete piles.
The installation of monolithic grillage has been completed.
Installation of vertical elements of the 1st floor is 80% complete.
Section 2
Works on pressing of reinforced concrete piles have been completed.
Section 1
Work has begun on the installation of monolithic grillage.
Work has begun on the pressing of reinforced concrete piles.
Find out first about the company's news