Section 1
Entrances are 95% complete.
Installation of heating networks is 95% complete.
Section 2
Installation of aluminum facade glazing is 90% complete.
Parking lot
Installation of waterproofing of the parking lot is in progress.
Landscaping
Landscaping and paving are in progress.