Section 1
Facade works on the commercial floor are 80% complete.
Section 2
Installation of a hinged-ventilated facade is completed.
Car park
Finishing of the car park is 60% complete
Installation of engineering networks has begun.
Landscaping
Landscaping is 90% complete.
Fencing is completed.