Sections 1-2
Completion of the exterior walls of the 9th floor.
Laying of the internal walls of the 8th and 9th floors has begun.
Concreting of vertical elements of the 13th floor is in progress.
Glazing of the 7th floor is in progress.
Plastering of apartments on floors 1-3 is in progress.
Section 3
Concreting of the basement floor slab is completed.
Concreting of vertical elements of the 1st floor is in progress.