The masonry of the outer walls of the 7th floor has been completed.
The laying of the internal walls of the 6th and 7th floors is in progress.
Concreting of the vertical elements of the 10th floor has been completed.
Reinforcement of the floor slab on the 10th floor is underway.
Glazing of the 3rd floor has begun.