0
We will call you back in 25 seconds
Order a call

Construction state of the Family Plaza residential complex as of 15.11.2023

Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023
Construction state of the Family Plaza residential complex as of 15.11.2023

01 /01

Section 3 Transferred to the management company. The hall is 99% finished. Section 4 Transferred to the management company. The lobby is 99% finished. Section 5 The hall is 95% finished. Section 6 Finishing of the entrance is 70% complete. Section 7 Finishing of the facade is completed. Finishing of balconies has begun. Finishing of the entrance is 50% complete. Section 8 Roofing works have been completed by 70%. The masonry of the internal walls of the 10th floor has been completed. Plastering of the apartments on the 8th, 9th and 10th floors has been completed. Plastering of the staircase has begun. Installation of internal power supply networks has begun. Installation of internal water supply and sewage networks is in progress. Sections 9-10 All monolithic works have been completed. Installation of vertical elements of the technical floor is completed. Installation of the technical floor slab is completed. Laying of the external walls of the 9th and 10th floors has been completed. Completion of the internal walls of the 3rd floor. Glazing from the 4th to the 8th floor has been completed. Installation of a sloping semi-dry roof screed has begun. Section 12 The lobby is 95% finished. Car park Roofing works are 90% complete.
envelope

Find out first about the company's news

close form

Даруємо квартиру за донат!

Даруємо квартиру за донат!